ENVIRONMENTAL APPRAISAL

A marine licence application and supporting Environmental Appraisal for the marine works was submitted to NRW in November 2018. It is anticipated that the application will take around 4 months for NRW to determine.

You can view the report here (appendices here).

SCREENING AND SCOPING REPORT

A Screening and Scoping Report was submitted to Natural Resources Wales in May to seek an opinion on the need for and scope of any further assessment work. NRW provided their Screening Opinion in July which determined that the project does not require a statutory Environmental Impact Assessment.

You can view the report here.