WORK SO FAR

WHERE WE ARE NOW – JULY 2021

 

  • Updated NRW marine licence obtained 27th March 2020

  • WG approval, application submitted 8th April 2020. Approval granted, 22 June 2020

  • Stage 2 on site construction, commenced 4th August with mobilisation and enabling works

  • Piling scheduled to commence early September 2020

  • Project completion scheduled for September 2021 

  • Covid-19, update, the project continues as planned, stakehloder meetings have been postponed until further notice

       

WORK SO FAR