WORK SO FAR
WHERE WE ARE NOW – FEBRUARY 2021
-
Updated NRW marine licence obtained 27th March 2020
-
WG approval, application submitted 8th April 2020. Approval granted, 22 June 2020
-
Stage 2 on site construction, commenced 4th August with mobilisation and enabling works
-
Piling scheduled to commence early September 2020
-
Project completion scheduled for June 2021
-
Covid-19, update, the project continues as planned, stakehloder meetings have been postponed until further notice